AALAYATACTICAL LAB← C2

STRATA · RUNWAY REPAIR

The fastest plan, and the proof that none is faster.

After an attack the first need is a minimum operating strip (MOS) aircraft can use. On a damage map this decides three things: where the strip goes, which unexploded ordnance (UXO) is cleared first, and how craters are shared between repair crews. Then it lays out, item by item, the evidence that this really is the fastest.

  • Task times, safety distances and machine sets are illustrative; Rapid-set cap to aircraft traffic: system default 30 min (assumed, to be confirmed by the using unit) | published guidance 120 min at 4.5 °C and above
  • Same seed, same result, for anyone
Excavators3
Wheel loaders / skid-steers3
Dump trucks6
Vibratory rollers / compactors3
Mobile concrete mixers3
Tractor + crane (mat sets)3
Mats in stock (craters)2
Sweepers1
Survey drones2
EOD teams1

One repair set = 1 excavator (clears broken slab, shapes the crater) + 1 wheel loader or skid-steer (places the fill) + 2 dump trucks (bring aggregate) + 1 vibratory roller (compacts the fill to bearing strength) + 1 mobile concrete mixer (stone-and-grout or high-strength rapid-set cement) + 1 heavy tractor with crane (places the FRP or AM2 mat as the temporary surface). The fleet forms 3 sets; the limit is excavators, wheel loaders / skid-steers, dump trucks, vibratory rollers / compactors, mobile concrete mixers, tractor + crane (mat sets).

Assessment time (2 drones): drone survey 12 min; sensing runway 7 min (3 min to place the impacts + confirmation). A sensing runway has distributed acoustic sensing (DAS) fibre and impact sensors laid along and across it, about NT$ 90–300 M per runway (estimate); times and cost are illustrative.

Everything below is computed live in your browser; change any setting and it recomputes. Seed 5

Recommended plan

Whole strip open

2 h 24 min

= drone damage assessment 12 min + clearance and repairs 1 h 32 min + cure and joint sealing 40 min (sweep in parallel)

First take-off 1 h 7 min · 900 m take-off segment opens at 1 h 7 min; light aircraft launch first

No mats on this map: the extra placement time would not pay back.

✓ Proven optimalOf 155 possible strip positions only 20 needed a full calculation; every other one is proven unable to be faster.✓ Take-off segment opening proven earliest · The whole strip can open at 2 h 23 min at best (proven); this plan gets aircraft out first and opens the whole strip 1 min later.0–1,500 m from the threshold, 15 m right of centre · 5 craters to repair, 1 UXO to clear first
Most aircraft out, soonest

No need to wait for the whole strip: once a stretch long enough for a take-off run is repaired and swept, lightly loaded aircraft can launch; heavy ones wait for the full length. The computer compares two plans and picks the one whose count of aircraft launched rises first.

Aircraft waiting12
Need full length4
Take-off segment (m)900
PlanFirst take-offWhole strip openAll launchedAverage wait per aircraft
Whole strip first1 h 55 min2 h 23 min2 h 29 min2 h 10 min
Take-off segment firstRecommended1 h 7 min2 h 24 min2 h 30 min1 h 38 min

Recommended: “Take-off segment first”. Aircraft launch 32 min earlier on average.

0246810120306090120150Minutes from startaircraft
  • Whole strip first · 2 h 29 min
  • Take-off segment first · 2 h 30 min

In “take-off segment first”, the segment's opening time is proven earliest; the order of the remaining craters after it is the fastest of the orders tried, not proven optimal.

Readiness and budget report: twelve damage scenarios, four readiness levels — what to buy, what it costs, how fast how many aircraft get off →

2-minute take-off interval; take-off segment 900 m by default (a loaded F-16A's afterburner take-off roll is about 725 m). Aircraft numbers are adjustable and illustrative; taxi routes from the shelters to the strip are assumed usable.

Drone orthophoto: damage read-out and repair plan

The survey drones photograph the whole runway and stitch it into one orthophoto; the computer reads the craters and UXO from it, and their positions and sizes are the same data the plan above uses. Click a crater or UXO for its close-up and tasking; drag the time slider to see the site at any moment.

Detected: 20 craters, 4 UXO / mine sites
0 min after start

Drag sideways

Damage and strip
C1 · ⌀3 m · 25 minC2 · ⌀14 m · 1 h 4 minC3 · ⌀16 m · 1 h 16 minC4 · ⌀3 m · 25 minC5 · ⌀5 m · 25 minC6 · ⌀13 m · 1 h 19 minC7 · ⌀8 m · 44 minC8 · ⌀13 m · 1 h 7 minC9 · ⌀6 m · 47 minC10 · ⌀18 m · 1 h 13 minC11 · ⌀13 m · 1 h 10 minC12 · ⌀18 m · 1 h 15 minC13 · ⌀5 m · 23 minC14 · ⌀8 m · 45 minC15 · ⌀9 m · 48 minC16 · ⌀8 m · 50 minC17 · ⌀5 m · 26 minC18 · ⌀8 m · 42 minC19 · ⌀9 m · 47 minC20 · ⌀16 m · 1 h 11 minC8C9C10C13U1 · r 40 m · 24 minU1U2 · r 30 m · 21 minU2U3 · r 38 m · 33 minU3U4 · r 28 m · 44 minU40 m50010001500200025003000Threshold (shelter end)
  • Crater to repair
  • Other crater
  • UXO and safety area
  • Recommended strip

Schematic: length compressed, width enlarged; craters are symbols sized by small / medium / large. Orange areas are UXO safety distances; craters inside one wait for clearance.

Damage map · seed 5 · 3 repair crews, 1 EOD team · 3 excavators · 3 loaders · 6 trucks · 3 rollers · 3 mixers · 3 mat sets · mats for 2 craters · 1 sweeper · 2 survey drones · Surface: cement, with mats on up to 2 craters

Schedule: who does what, when
0306090120minutesSurvey drone 1Damage map · 0–12Damage mapSurvey drone 2Damage map · 0–12Damage mapEOD 1U1 · 12–36U1Machine set 1C4 · 12–37C4C8 · 37–104C8Machine set 2C5 · 12–37C5C9 · 37–84C9Machine set 3C10 · 12–85C10C4 cureCure · 37–57CureSeal · 57–67SealC5 cureCure · 37–57CureSeal · 57–67SealC10 cureCure · 85–105CureSeal · 105–115SealC8 cureCure · 104–124CureSeal · 124–134SealC9 cureCure · 84–104CureSeal · 104–114SealSweeper 1Sweep · 104–144SweepFirst take-off 1 h 7 minStrip open 2 h 24 min

Each row is a drone, a team or a machine set. Drones map the damage first, then clearance and repairs (machines and people stay outside UXO safety radii); a machine set moves on as soon as a crater is done, the crater cures and is then sealed by hand, and the sweep runs during the cure; the strip opens at the line on the right.

Damage map · seed 5 · 3 repair crews, 1 EOD team · 3 excavators · 3 loaders · 6 trucks · 3 rollers · 3 mixers · 3 mat sets · mats for 2 craters · 1 sweeper · 2 survey drones · Surface: cement, with mats on up to 2 craters · proven-fastest schedule

Which surface

Same damage, same machines, re-solved to the best for each surface. Rapid-set cement lasts and carries traffic in about 30 min (assumed; published guidance 120 min); asphalt needs about 45 min to cool and a hot-mix source; mats need no cure but are few and temporary.

Computing…

Damage map · seed 5 · 3 repair crews, 1 EOD team · 3 excavators · 3 loaders · 6 trucks · 3 rollers · 3 mixers · 3 mat sets · mats for 2 craters · 1 sweeper · 2 survey drones

Base-defence unit runway repair procedure

Runway repair: slab grid, MOS options, shelter access and launch sequence

The runway is laid in slabs: rows A, B, C … across and columns 1, 2, 3 … along, and every crater and UXO is named by its slab code. The minimum operating strip (MOS) is at least 5,000 ft × 50 ft and may lie at an angle as long as it stays on the pavement. At least three repair options are always put forward, each with its completion time, crews and machines, and materials. A crater on the taxi route from a shelter to the MOS must be repaired too, or that shelter's aircraft cannot launch.

  • Base layout assumed: north and south shelter groups, until the unit provides real data
  • Slab size 7.5 × 7.5 m by default, to be confirmed by the unit
  • Camouflet repair time, taxi speed, take-off spacing and route sweep time are assumptions

Damage assessment session (SOP-A: paper forms and field phones)

Runway slabs: 6 rows × 400 columns. Current damage: Large crater 0, Small crater 0, Camouflet 0, UXO 0. A camouflet must be dug out before its size is known; the schedule always uses the longest time (conservative).

Runway slab map, shelters and access routes

NSN1S1N2S2N3S3N4S4N5S5NPSPABCDEF14181121161201241281321361×2N-01×2N-02×1N-03×1N-04×2S-01×1S-02×2S-03×1S-04North shelter group (assumed layout)South shelter group (assumed layout)Threshold 0 m3000 m
  • Large crater6 m across or more (threshold assumed)
  • Small craterunder 6 m across
  • Camoufletsmall surface hole, hollow below; dig out to assess; repair time is a range
  • UXOsafety radius shown; no work inside until cleared
  • MOS option (solid: option in view)
  • Route clear
  • Route needs repair (blocked)
  • Shelter (× aircraft)
  • UXO blast ring: craters inside wait until it is clearedassumed
  • UXO fragmentation ring: people leave it during disposalassumed

The runway is stretched across so the slab rows and the small MOS angles show; taxiways and shelters outside it are compressed. Column numbers are marked every few dozen columns here; every slab shows in the image overlay below. Slabs 7.5 × 7.5 m (assumption). Select damage to view it in the overlay.

MOS repair options (at least three)

Unit rule: MOS at least 5,000 ft × 50 ft (1524 m × 15.2 m), parallel to the centre line or at an angle, wholly on the runway pavement; at least 3 options are put to the commander every time.

Computing options…

Damage form and runway image

Left: the paper damage form, digitised (its fields follow the unit's form and can be changed). Right: the runway image with the slab grid, each crater photo placed to scale where it lies. Select a row or a damage point to find it in the other view.

Runway damage record

Base: (assumed)Runway: 09/27Slabs 7.5 × 7.5 m, rows A–F, columns 1–4000 entries
Print blank form
Form fields (to match the unit's form)
#Slab codeDamage typeSizeNotesTime recordedRecorded by
No damage recorded.

Runway orthophoto; slab grid, codes and photos overlaid to scale. A field photo is sized from the reported size (assumes the crater spans about 60% of the photo's width).

Select a form row or damage in the image for its close-up and repair assignment.

Field report entry

Before drones are fielded, personnel on the runway enter damage by slab code, or take a photo on a phone or tablet and mark its position on the image. Options and the launch sequence recompute at once.

Is it really the fastest?

An exact operations-research algorithm (branch and bound) computed this answer, and every step can be checked. Each of the five checks below can be re-run and challenged.

① Upper and lower bounds converge

While solving, two numbers are tracked: how long the best plan found so far takes (upper bound, only goes down) and how fast any plan could possibly be (lower bound, only goes up). When the two lines meet, that is a proof, not a guess.

  • Upper bound: best plan so far
  • Lower bound: nothing can be faster
120130140150160Lines meet at 2 h 11 min: proven optimalStrip positions fully calculated02468101214161820

Damage map · seed 5 · 3 repair crews, 1 EOD team · 3 excavators · 3 loaders · 6 trucks · 3 rollers · 3 mixers · 3 mat sets · mats for 2 craters · 1 sweeper · 2 survey drones · Surface: cement, with mats on up to 2 craters · branch and bound: 20 of 155 strips solved in full

Data table
#Upper bound: best plan so farLower bound: nothing can be faster
0—2 h 8 min
12 h 34 min2 h 8 min
22 h 34 min2 h 8 min
32 h 34 min2 h 11 min
42 h 12 min2 h 11 min
52 h 12 min2 h 11 min
62 h 12 min2 h 11 min
72 h 12 min2 h 11 min
82 h 12 min2 h 11 min
92 h 12 min2 h 11 min
102 h 12 min2 h 11 min
112 h 12 min2 h 11 min
122 h 12 min2 h 11 min
132 h 12 min2 h 11 min
142 h 12 min2 h 11 min
152 h 12 min2 h 11 min
162 h 12 min2 h 11 min
172 h 12 min2 h 11 min
182 h 12 min2 h 11 min
192 h 12 min2 h 11 min
202 h 11 min2 h 11 min

② Why each position cannot be faster

Every possible strip position has a lower bound no ordering can beat, with a one-line reason. Grey bars sit above the blue line and need no detailed calculation; the few below it were fully calculated and are also confirmed slower.

  • Recommended position
  • Fully calculated
  • Bound already above the answer
050100150200250MOS-450-L7.5 · 4 craters, 262 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 8 min.MOS-500-L7.5 · 4 craters, 262 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 8 min.MOS-550-L7.5 · 4 craters, 262 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 8 min.MOS-0-R15 · Crater C8 lies inside the safety area of UXO U1: at least 24 min of clearance, then 67 min of repair, then at least 40 min of cure, mat or sweep, so no earlier than 2 h 11 min.MOS-50-R15 · Crater C8 lies inside the safety area of UXO U1: at least 24 min of clearance, then 67 min of repair, then at least 40 min of cure, mat or sweep, so no earlier than 2 h 11 min.MOS-100-R15 · Crater C8 lies inside the safety area of UXO U1: at least 24 min of clearance, then 67 min of repair, then at least 40 min of cure, mat or sweep, so no earlier than 2 h 11 min.MOS-150-R15 · Crater C8 lies inside the safety area of UXO U1: at least 24 min of clearance, then 67 min of repair, then at least 40 min of cure, mat or sweep, so no earlier than 2 h 11 min.MOS-200-R15 · Crater C8 lies inside the safety area of UXO U1: at least 24 min of clearance, then 67 min of repair, then at least 40 min of cure, mat or sweep, so no earlier than 2 h 11 min.MOS-250-R15 · Crater C8 lies inside the safety area of UXO U1: at least 24 min of clearance, then 67 min of repair, then at least 40 min of cure, mat or sweep, so no earlier than 2 h 11 min.MOS-300-R15 · Crater C8 lies inside the safety area of UXO U1: at least 24 min of clearance, then 67 min of repair, then at least 40 min of cure, mat or sweep, so no earlier than 2 h 11 min.MOS-350-R15 · Crater C8 lies inside the safety area of UXO U1: at least 24 min of clearance, then 67 min of repair, then at least 40 min of cure, mat or sweep, so no earlier than 2 h 11 min.MOS-400-R15 · Crater C8 lies inside the safety area of UXO U1: at least 24 min of clearance, then 67 min of repair, then at least 40 min of cure, mat or sweep, so no earlier than 2 h 11 min.MOS-450-C0 · Crater C8 lies inside the safety area of UXO U1: at least 24 min of clearance, then 67 min of repair, then at least 40 min of cure, mat or sweep, so no earlier than 2 h 11 min.MOS-450-R7.5 · Crater C8 lies inside the safety area of UXO U1: at least 24 min of clearance, then 67 min of repair, then at least 40 min of cure, mat or sweep, so no earlier than 2 h 11 min.MOS-450-R15 · Crater C8 lies inside the safety area of UXO U1: at least 24 min of clearance, then 67 min of repair, then at least 40 min of cure, mat or sweep, so no earlier than 2 h 11 min.MOS-500-C0 · Crater C8 lies inside the safety area of UXO U1: at least 24 min of clearance, then 67 min of repair, then at least 40 min of cure, mat or sweep, so no earlier than 2 h 11 min.MOS-500-R7.5 · Crater C8 lies inside the safety area of UXO U1: at least 24 min of clearance, then 67 min of repair, then at least 40 min of cure, mat or sweep, so no earlier than 2 h 11 min.MOS-500-R15 · Crater C8 lies inside the safety area of UXO U1: at least 24 min of clearance, then 67 min of repair, then at least 40 min of cure, mat or sweep, so no earlier than 2 h 11 min.MOS-550-C0 · Crater C8 lies inside the safety area of UXO U1: at least 24 min of clearance, then 67 min of repair, then at least 40 min of cure, mat or sweep, so no earlier than 2 h 11 min.MOS-550-R7.5 · Crater C8 lies inside the safety area of UXO U1: at least 24 min of clearance, then 67 min of repair, then at least 40 min of cure, mat or sweep, so no earlier than 2 h 11 min.MOS-550-R15 · Crater C8 lies inside the safety area of UXO U1: at least 24 min of clearance, then 67 min of repair, then at least 40 min of cure, mat or sweep, so no earlier than 2 h 11 min.MOS-600-R15 · Crater C8 lies inside the safety area of UXO U1: at least 24 min of clearance, then 67 min of repair, then at least 40 min of cure, mat or sweep, so no earlier than 2 h 11 min.MOS-650-R15 · Crater C8 lies inside the safety area of UXO U1: at least 24 min of clearance, then 67 min of repair, then at least 40 min of cure, mat or sweep, so no earlier than 2 h 11 min.MOS-700-R15 · Crater C8 lies inside the safety area of UXO U1: at least 24 min of clearance, then 67 min of repair, then at least 40 min of cure, mat or sweep, so no earlier than 2 h 11 min.MOS-1000-L7.5 · 3 UXO must be cleared first; 1 EOD team need at least 98 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 18 min.MOS-1000-C0 · 3 UXO must be cleared first; 1 EOD team need at least 98 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 18 min.MOS-1000-R7.5 · 3 UXO must be cleared first; 1 EOD team need at least 98 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 18 min.MOS-1000-R15 · 3 UXO must be cleared first; 1 EOD team need at least 98 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 18 min.MOS-1050-L7.5 · 3 UXO must be cleared first; 1 EOD team need at least 98 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 18 min.MOS-1050-C0 · 3 UXO must be cleared first; 1 EOD team need at least 98 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 18 min.MOS-1050-R7.5 · 3 UXO must be cleared first; 1 EOD team need at least 98 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 18 min.MOS-1050-R15 · 3 UXO must be cleared first; 1 EOD team need at least 98 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 18 min.MOS-1100-R15 · 3 UXO must be cleared first; 1 EOD team need at least 98 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 18 min.MOS-1150-R15 · 3 UXO must be cleared first; 1 EOD team need at least 98 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 18 min.MOS-1200-R15 · 3 UXO must be cleared first; 1 EOD team need at least 98 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 18 min.MOS-1250-R15 · 3 UXO must be cleared first; 1 EOD team need at least 98 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 18 min.MOS-1300-R15 · 3 UXO must be cleared first; 1 EOD team need at least 98 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 18 min.MOS-1350-R15 · 3 UXO must be cleared first; 1 EOD team need at least 98 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 18 min.MOS-1400-R15 · 3 UXO must be cleared first; 1 EOD team need at least 98 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 18 min.MOS-1450-R15 · 3 UXO must be cleared first; 1 EOD team need at least 98 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 18 min.MOS-1500-R15 · 3 UXO must be cleared first; 1 EOD team need at least 98 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 18 min.MOS-600-R7.5 · 6 craters, 308 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 23 min.MOS-650-R7.5 · 6 craters, 308 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 23 min.MOS-700-R7.5 · 6 craters, 308 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 23 min.MOS-1500-L15 · 5 craters, 309 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 23 min.MOS-1500-R7.5 · 7 craters, 309 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 23 min.MOS-600-L7.5 · 5 craters, 310 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 24 min.MOS-650-L7.5 · 5 craters, 310 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 24 min.MOS-700-L7.5 · 5 craters, 310 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 24 min.MOS-1000-L15 · 5 craters, 311 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 24 min.MOS-1050-L15 · 5 craters, 311 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 24 min.MOS-0-R7.5 · 6 craters, 313 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 25 min.MOS-50-R7.5 · 6 craters, 313 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 25 min.MOS-100-R7.5 · 6 craters, 313 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 25 min.MOS-150-R7.5 · 6 craters, 313 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 25 min.MOS-200-R7.5 · 6 craters, 313 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 25 min.MOS-250-R7.5 · 6 craters, 313 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 25 min.MOS-1100-C0 · 6 craters, 314 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 25 min.MOS-1150-C0 · 6 craters, 314 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 25 min.MOS-1200-C0 · 6 craters, 314 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 25 min.MOS-1250-C0 · 6 craters, 314 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 25 min.MOS-1300-C0 · 6 craters, 314 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 25 min.MOS-1350-C0 · 6 craters, 314 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 25 min.MOS-1400-C0 · 6 craters, 314 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 25 min.MOS-1450-C0 · 6 craters, 314 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 25 min.MOS-1500-C0 · 6 craters, 314 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 25 min.MOS-0-L7.5 · 5 craters, 327 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 29 min.MOS-0-C0 · 5 craters, 330 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 30 min.MOS-50-C0 · 5 craters, 330 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 30 min.MOS-100-C0 · 5 craters, 330 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 30 min.MOS-150-C0 · 5 craters, 330 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 30 min.MOS-200-C0 · 5 craters, 330 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 30 min.MOS-250-C0 · 5 craters, 330 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 30 min.MOS-300-C0 · 5 craters, 330 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 30 min.MOS-350-C0 · 5 craters, 330 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 30 min.MOS-400-C0 · 5 craters, 330 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 30 min.MOS-300-R7.5 · 7 craters, 336 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 32 min.MOS-350-R7.5 · 7 craters, 336 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 32 min.MOS-400-R7.5 · 7 craters, 336 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 32 min.MOS-400-L7.5 · 5 craters, 338 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 33 min.MOS-450-L15 · 5 craters, 341 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 34 min.MOS-500-L15 · 5 craters, 341 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 34 min.MOS-550-L15 · 5 craters, 341 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 34 min.MOS-600-C0 · 6 craters, 352 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 38 min.MOS-650-C0 · 6 craters, 352 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 38 min.MOS-700-C0 · 6 craters, 352 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 38 min.MOS-1100-R7.5 · 8 craters, 356 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 39 min.MOS-1150-R7.5 · 8 craters, 356 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 39 min.MOS-1200-R7.5 · 8 craters, 356 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 39 min.MOS-1250-R7.5 · 8 craters, 356 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 39 min.MOS-1300-R7.5 · 8 craters, 356 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 39 min.MOS-1350-R7.5 · 8 craters, 356 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 39 min.MOS-1400-R7.5 · 8 craters, 356 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 39 min.MOS-1450-R7.5 · 8 craters, 356 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 39 min.MOS-750-L7.5 · 4 UXO must be cleared first; 1 EOD team need at least 122 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 42 min.MOS-750-C0 · 4 UXO must be cleared first; 1 EOD team need at least 122 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 42 min.MOS-750-R7.5 · 4 UXO must be cleared first; 1 EOD team need at least 122 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 42 min.MOS-750-R15 · 4 UXO must be cleared first; 1 EOD team need at least 122 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 42 min.MOS-800-L7.5 · 4 UXO must be cleared first; 1 EOD team need at least 122 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 42 min.MOS-800-R7.5 · 4 UXO must be cleared first; 1 EOD team need at least 122 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 42 min.MOS-800-R15 · 4 UXO must be cleared first; 1 EOD team need at least 122 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 42 min.MOS-850-L7.5 · 4 UXO must be cleared first; 1 EOD team need at least 122 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 42 min.MOS-850-R7.5 · 4 UXO must be cleared first; 1 EOD team need at least 122 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 42 min.MOS-850-R15 · 4 UXO must be cleared first; 1 EOD team need at least 122 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 42 min.MOS-900-L7.5 · 4 UXO must be cleared first; 1 EOD team need at least 122 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 42 min.MOS-900-R7.5 · 4 UXO must be cleared first; 1 EOD team need at least 122 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 42 min.MOS-900-R15 · 4 UXO must be cleared first; 1 EOD team need at least 122 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 42 min.MOS-950-L15 · 4 UXO must be cleared first; 1 EOD team need at least 122 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 42 min.MOS-950-L7.5 · 4 UXO must be cleared first; 1 EOD team need at least 122 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 42 min.MOS-950-C0 · 4 UXO must be cleared first; 1 EOD team need at least 122 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 42 min.MOS-950-R7.5 · 4 UXO must be cleared first; 1 EOD team need at least 122 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 42 min.MOS-950-R15 · 4 UXO must be cleared first; 1 EOD team need at least 122 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 42 min.MOS-800-C0 · 7 craters, 378 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 46 min.MOS-850-C0 · 7 craters, 378 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 46 min.MOS-900-C0 · 7 craters, 378 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 46 min.MOS-1100-L15 · 6 craters, 382 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 48 min.MOS-1100-L7.5 · 6 craters, 384 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 48 min.MOS-1150-L15 · 6 craters, 382 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 48 min.MOS-1150-L7.5 · 6 craters, 384 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 48 min.MOS-1200-L15 · 6 craters, 382 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 48 min.MOS-1200-L7.5 · 6 craters, 384 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 48 min.MOS-1250-L15 · 6 craters, 382 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 48 min.MOS-1250-L7.5 · 6 craters, 384 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 48 min.MOS-1300-L15 · 6 craters, 382 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 48 min.MOS-1300-L7.5 · 6 craters, 384 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 48 min.MOS-1350-L15 · 6 craters, 382 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 48 min.MOS-1350-L7.5 · 6 craters, 384 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 48 min.MOS-1400-L15 · 6 craters, 382 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 48 min.MOS-1400-L7.5 · 6 craters, 384 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 48 min.MOS-1450-L15 · 6 craters, 382 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 48 min.MOS-1450-L7.5 · 6 craters, 384 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 48 min.MOS-1500-L7.5 · 6 craters, 384 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 48 min.MOS-50-L7.5 · 6 craters, 402 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 54 min.MOS-100-L7.5 · 6 craters, 402 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 54 min.MOS-150-L7.5 · 6 craters, 402 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 54 min.MOS-200-L7.5 · 6 craters, 402 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 54 min.MOS-250-L7.5 · 6 craters, 402 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 54 min.MOS-300-L7.5 · 6 craters, 402 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 54 min.MOS-350-L7.5 · 6 craters, 402 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 54 min.MOS-400-L15 · 6 craters, 417 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 2 h 59 min.MOS-0-L15 · 7 craters, 431 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 3 h 4 min.MOS-600-L15 · 7 craters, 434 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 3 h 5 min.MOS-650-L15 · 7 craters, 434 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 3 h 5 min.MOS-700-L15 · 7 craters, 434 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 3 h 5 min.MOS-750-L15 · 7 craters, 434 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 3 h 5 min.MOS-800-L15 · 7 craters, 434 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 3 h 5 min.MOS-850-L15 · 7 craters, 434 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 3 h 5 min.MOS-900-L15 · 7 craters, 434 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 3 h 5 min.MOS-350-L15 · 7 craters, 481 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 3 h 21 min.MOS-50-L15 · 8 craters, 506 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 3 h 29 min.MOS-100-L15 · 8 craters, 506 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 3 h 29 min.MOS-150-L15 · 8 craters, 506 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 3 h 29 min.MOS-200-L15 · 8 craters, 506 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 3 h 29 min.MOS-250-L15 · 8 craters, 506 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 3 h 29 min.MOS-300-L15 · 8 craters, 506 crew-minutes of work: even with 3 crews at once, plus at least 40 min of cure or sweep at the end, it takes at least 3 h 29 min.Recommended 2 h 11 min

Damage map · seed 5 · 3 repair crews, 1 EOD team · 3 excavators · 3 loaders · 6 trucks · 3 rollers · 3 mixers · 3 mat sets · mats for 2 craters · 1 sweeper · 2 survey drones · Surface: cement, with mats on up to 2 craters · lower bounds for all 155 candidate strips

Closest alternatives (fully calculated)

  1. 0–1,500 m from the threshold, 15 m right of centreBest 2 h 12 min, 1 min slower than the recommendation · Crater C8 lies inside the safety area of UXO U1: at least 24 min of clearance, then 67 min of repair, then at least 40 min of cure, mat or sweep, so no earlier than 2 h 11 min.5 neighbouring positions need the same repairs, same result
  2. 450–1,950 m from the threshold, 7.5 m right of centreBest 2 h 12 min, 1 min slower than the recommendation · Crater C8 lies inside the safety area of UXO U1: at least 24 min of clearance, then 67 min of repair, then at least 40 min of cure, mat or sweep, so no earlier than 2 h 11 min.3 neighbouring positions need the same repairs, same result
  3. 300–1,800 m from the threshold, 15 m right of centreBest 2 h 15 min, 4 min slower than the recommendation · Crater C8 lies inside the safety area of UXO U1: at least 24 min of clearance, then 67 min of repair, then at least 40 min of cure, mat or sweep, so no earlier than 2 h 11 min.2 neighbouring positions need the same repairs, same result
  4. 600–2,100 m from the threshold, 15 m right of centreBest 2 h 17 min, 6 min slower than the recommendation · Crater C8 lies inside the safety area of UXO U1: at least 24 min of clearance, then 67 min of repair, then at least 40 min of cure, mat or sweep, so no earlier than 2 h 11 min.
  5. 650–2,150 m from the threshold, 15 m right of centreBest 2 h 17 min, 6 min slower than the recommendation · Crater C8 lies inside the safety area of UXO U1: at least 24 min of clearance, then 67 min of repair, then at least 40 min of cure, mat or sweep, so no earlier than 2 h 11 min.1 neighbouring position need the same repairs, same result
  6. 1,000–2,500 m from the threshold, on the centre lineBest 2 h 18 min, 7 min slower than the recommendation · 3 UXO must be cleared first; 1 EOD team need at least 98 min, then at least 40 min of cure, mat or sweep: no earlier than 2 h 18 min.1 neighbouring position need the same repairs, same result

③ Against other ways of ordering

Same damage, same people, scheduled by common whiteboard rules. Then 10,000 random feasible plans: the optimum should sit at the far left with nothing beating it.

  • Optimum (proven)
    2 h 11 min
  • Near to farStart at the shelter end and repair in order of distance
    2 h 33 min22 min slower (+17%)
  • Biggest firstLeast-damaged strip, largest craters first
    2 h 20 min9 min slower (+7%)
  • Clear all UXO firstClear every UXO on the runway before any repair
    4 h 22 min2 h 11 min slower (+100%)
  • Centre of the runwayThe strip at the runway centre, largest craters first
    3 h 10 min59 min slower (+45%)

Damage map · seed 5 · 3 repair crews, 1 EOD team · 3 excavators · 3 loaders · 6 trucks · 3 rollers · 3 mixers · 3 mat sets · mats for 2 craters · 1 sweeper · 2 survey drones · Surface: cement, with mats on up to 2 craters · four whiteboard rules, same damage map and crews

Finish times of 10,000 random feasible plans

Computing…

④ Two independent solvers must agree

Besides the solver in this page, Google OR-Tools (CP-SAT) re-builds the model from the raw geometry and solves it independently. The answers must match exactly; the comparison is part of the automated tests, so any code change that breaks it is stopped.

  • 100 random damage maps, 1–6 repair crews, 1–2 EOD teams: all 100 match
  • Small cases also checked by enumerating every ordering (brute force): match
  • Cure, sealing, the sweep and which craters get mats checked by enumerating every ordering and every mat choice: match
  • Every position's lower bound is verified never to exceed its true fastest time

⑤ Does the answer hold when assumptions change?

"Optimal" holds only while the assumptions hold. Repair times, clearance times and crew numbers are assumptions, so change one at a time and see whether the recommendation moves.

Computing…

The sweet spot: how many crews actually help

Same damage, repair crews from 1 to 6 with one or two EOD teams; every point is a proven fastest time. Where the curve flattens is the sweet spot: more people barely change the time.

Computing…

Method and limits

  • Problem: pick a 1,500 × 15 m minimum operating strip (155 candidate positions), order UXO clearance, and assign craters to crews so the strip opens as early as possible.
  • Algorithm: branch and bound. Every candidate position gets a lower bound; positions are solved exactly in order of bound until the best plan is no slower than every remaining bound.
  • Waits after a repair: high-strength rapid-set cement reaches initial set 10–15 min after the pour and carries fighters about 30 min after it (system default, assumed; 20 min cure plus 10 min hand joint sealing; the older US DoD rapid-setting concrete figure, TSPWG 3-270-01.21-05, is 2 h); the 45 min asphalt cool-down is illustrative; an FRP or AM2 mat adds 15 min of placement per crater and needs no cure. Machine sets do not wait for a cure: they go to the next crater, and the sweep runs during the cure.
  • Not modelled: travel of people and vehicles, night and weather, equipment failure, re-attack. Real use calibrates these parameters to unit doctrine.