C2 · Runway repair · simulation

Runway damage AI: one look, then what to send

After the drones fly over the runway, the damage assessment must answer three things: where it is broken, how big, and what to send. This page uses the planning page's own damage and the same minimum-operating-strip solver to compare two AI versions; whether each crater and UXO is found, the size estimate and the false alarms are all taken from figures measured on overhead images rendered in Isaac Sim.

All simulation: detection figures come from synthetic images (procedural geometry, modelled thermal); no field or real-aircraft validation.

AI version
Runway damage map (3,000 m long, 45 m wide, width exaggerated)
  • Crater found (ring = estimated size)
  • Crater missed
  • UXO (dashed = safety radius)
  • UXO missed
  • False alarm taken as damage (not struck off)
  • Chosen minimum operating strip
From flyover to repair plan
  1. Survey flight (two drones, same for both)12 min
  2. Image processing (213 frames, 4 CPU threads)150.8 min
  3. A person checks candidates (957, 8 s each, assumed)127.6 min
  4. Solve the strip and the schedule0.1 min

Flyover to plan: 278.5 min

What to send (each crater in the strip)

ItemDiameterDepth (range)MethodMachinesMaterialsCure countdown
C96.5 mNot estimated (standard excavation depth)Flowable fill + rapid-set capCompact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, ScreedFlowable fill 20 bags, Rapid-set cement 15 bags30 min
C108.0 mNot estimated (standard excavation depth)Flowable fill + rapid-set capCompact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, ScreedFlowable fill 30 bags, Rapid-set cement 22 bags30 min
C119.2 mNot estimated (standard excavation depth)Flowable fill + rapid-set capCompact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, ScreedFlowable fill 40 bags, Rapid-set cement 29 bags30 min
C1511.1 mNot estimated (standard excavation depth)Flowable fill + rapid-set capCompact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, ScreedFlowable fill 58 bags, Rapid-set cement 41 bags30 min
C164.5 mNot estimated (standard excavation depth)Flowable fill + rapid-set capCompact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, ScreedFlowable fill 10 bags, Rapid-set cement 7 bags30 min
C1720.3 mNot estimated (standard excavation depth)Flowable fill + rapid-set capCompact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, ScreedFlowable fill 192 bags, Rapid-set cement 137 bags30 min
C2227.2 mNot estimated (standard excavation depth)Flowable fill + rapid-set capCompact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, ScreedFlowable fill 345 bags, Rapid-set cement 246 bags30 min
C2319.6 mNot estimated (standard excavation depth)Flowable fill + rapid-set capCompact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, ScreedFlowable fill 179 bags, Rapid-set cement 128 bags30 min
C2417.6 mNot estimated (standard excavation depth)Flowable fill + rapid-set capCompact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, ScreedFlowable fill 145 bags, Rapid-set cement 103 bags30 min
F553.0 mNot estimated (standard excavation depth)Flowable fill + rapid-set capCompact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, ScreedFlowable fill 5 bags, Rapid-set cement 3 bags30 min
F1963.0 mNot estimated (standard excavation depth)Flowable fill + rapid-set capCompact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, ScreedFlowable fill 5 bags, Rapid-set cement 3 bags30 min
F3303.0 mNot estimated (standard excavation depth)Flowable fill + rapid-set capCompact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, ScreedFlowable fill 5 bags, Rapid-set cement 3 bags30 min
F3383.0 mNot estimated (standard excavation depth)Flowable fill + rapid-set capCompact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, ScreedFlowable fill 5 bags, Rapid-set cement 3 bags30 min
F3713.0 mNot estimated (standard excavation depth)Flowable fill + rapid-set capCompact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, ScreedFlowable fill 5 bags, Rapid-set cement 3 bags30 min
F3913.0 mNot estimated (standard excavation depth)Flowable fill + rapid-set capCompact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, ScreedFlowable fill 5 bags, Rapid-set cement 3 bags30 min
F5643.0 mNot estimated (standard excavation depth)Flowable fill + rapid-set capCompact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, ScreedFlowable fill 5 bags, Rapid-set cement 3 bags30 min
F6403.0 mNot estimated (standard excavation depth)Flowable fill + rapid-set capCompact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, ScreedFlowable fill 5 bags, Rapid-set cement 3 bags30 min
F8693.0 mNot estimated (standard excavation depth)Flowable fill + rapid-set capCompact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, ScreedFlowable fill 5 bags, Rapid-set cement 3 bags30 min
Materials the plan orders
Flowable fill 1052 bags, Rapid-set cement 752 bags, Fibreglass mat 0
Materials the real damage needs
Flowable fill 4036 bags, Rapid-set cement 322 bags, Fibreglass mat 0

Short: 0 bags of cement, 2984 bags of fill (another haul)

Methods, machines, material formulas and cure time come from the runway repair parameter table (version 2026.11-12); the solver decides which craters get the fibreglass mats.

What v2 changes, in plain words

  • The detector is replaced by one learned from rendered runway damage; it looks at visible and thermal together and uses the thermal image at night.
  • Each crater comes with a diameter and a depth, with an error range; material quantities use the estimated depth instead of always the standard excavation depth.
  • It also tells spall, sub-munitions, debris and standing water apart; the current detector has no such classes.
  • Everything else stays: a person still confirms each candidate, the strip and schedule use the same solver, methods and materials the same parameter table; v1's old runs replay unchanged.

Image-level measurement (576 test frames never used in training) · Seen in training

VersionFoundClass also rightFalse alarms per 1,000 m²Median relative diameter error
v1 current48.9%31.2%3.1452.3%
v2 physical AI70.5%70%0.266.1%

Comparison over 200 seeds (same damage) · Day · Seen in training

VersionCraters foundUXO foundFalse alarms per runDiameter error (mean / 90th pct)Flyover to planActual openingRuns with damage missed in the strip (of which UXO)Cement short (bags)
v1 current detector99.3%68.9%906.43.49 / 6.9 m275.1 min190 min43.5% (40.5%)0.0
v2 physical AI (learned detection + size and depth)82.9%84.9%30.80.44 / 1.2 m7.5 min157 min74% (19%)48.2

Where v2 is worse or not yet to be trusted

  • Day · Seen in training: Craters found v2 82.9%, v1 99.3%
  • Day · Seen in training: Runs with damage missed in the strip (of which UXO) v2 74% (19%), v1 43.5% (40.5%)
  • Day · Seen in training: Cement short (bags) v2 48.18, v1 0
  • Day · Unseen (asphalt, rocket-type UXO, ball sub-munitions, round patches): Craters found v2 79.6%, v1 97.7%
  • Day · Unseen (asphalt, rocket-type UXO, ball sub-munitions, round patches): Runs with damage missed in the strip (of which UXO) v2 84% (45%), v1 61% (55%)
  • Day · Unseen (asphalt, rocket-type UXO, ball sub-munitions, round patches): Cement short (bags) v2 62.58, v1 0
  • Night (thermal only) · Seen in training: Cement short (bags) v2 51.66, v1 31.85
  • Night (thermal only) · Unseen (asphalt, rocket-type UXO, ball sub-munitions, round patches): Craters found v2 65.4%, v1 71.3%
  • Night (thermal only) · Unseen (asphalt, rocket-type UXO, ball sub-munitions, round patches): Cement short (bags) v2 77.89, v1 39.74
  • Image level · Seen in training · large craters (10 m and over): Found v2 65.7%, v1 94.0%
  • Image level · Unseen (asphalt, rocket-type UXO, ball sub-munitions, round patches) · large craters (10 m and over): Found v2 57.7%, v1 84.6%
  • Image level · Seen in training · craters: Found v2 82.7%, v1 92.7%
  • Image level · Unseen (asphalt, rocket-type UXO, ball sub-munitions, round patches) · craters: Found v2 77.5%, v1 89.8%
  • Unseen conditions: v2's find rate drops from 70.5% to 66.9% and false alarms rise from 0.26 to 0.32 per 1,000 m²; measure on real imagery of a new pavement or munition before relying on it.
  • Every figure is measured on synthetic images; part of what the model learned may be features of this procedural geometry, and real-world performance is unknown.

Assumptions (not measured; other values may change the conclusion)

  • A person spends 8 s per candidate
  • A person wrongly accepts 10% of false alarms; each costs a crew 5 min
  • True crater depth = diameter × 0.25
  • Survey covers 75 m wide with 1.3× overlap; missed damage is found at the check before opening and then repaired