C2 · Runway repair · simulation
Runway damage AI: one look, then what to send
After the drones fly over the runway, the damage assessment must answer three things: where it is broken, how big, and what to send. This page uses the planning page's own damage and the same minimum-operating-strip solver to compare two AI versions; whether each crater and UXO is found, the size estimate and the false alarms are all taken from figures measured on overhead images rendered in Isaac Sim.
- Crater found (ring = estimated size)
- Crater missed
- UXO (dashed = safety radius)
- UXO missed
- False alarm taken as damage (not struck off)
- Chosen minimum operating strip
From flyover to repair plan
- Survey flight (two drones, same for both)12 min
- Image processing (213 frames, 4 CPU threads)150.8 min
- A person checks candidates (957, 8 s each, assumed)127.6 min
- Solve the strip and the schedule0.1 min
Flyover to plan: 278.5 min
What to send (each crater in the strip)
| Item | Diameter | Depth (range) | Method | Machines | Materials | Cure countdown |
|---|---|---|---|---|---|---|
| C9 | 6.5 m | Not estimated (standard excavation depth) | Flowable fill + rapid-set cap | Compact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, Screed | Flowable fill 20 bags, Rapid-set cement 15 bags | 30 min |
| C10 | 8.0 m | Not estimated (standard excavation depth) | Flowable fill + rapid-set cap | Compact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, Screed | Flowable fill 30 bags, Rapid-set cement 22 bags | 30 min |
| C11 | 9.2 m | Not estimated (standard excavation depth) | Flowable fill + rapid-set cap | Compact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, Screed | Flowable fill 40 bags, Rapid-set cement 29 bags | 30 min |
| C15 | 11.1 m | Not estimated (standard excavation depth) | Flowable fill + rapid-set cap | Compact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, Screed | Flowable fill 58 bags, Rapid-set cement 41 bags | 30 min |
| C16 | 4.5 m | Not estimated (standard excavation depth) | Flowable fill + rapid-set cap | Compact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, Screed | Flowable fill 10 bags, Rapid-set cement 7 bags | 30 min |
| C17 | 20.3 m | Not estimated (standard excavation depth) | Flowable fill + rapid-set cap | Compact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, Screed | Flowable fill 192 bags, Rapid-set cement 137 bags | 30 min |
| C22 | 27.2 m | Not estimated (standard excavation depth) | Flowable fill + rapid-set cap | Compact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, Screed | Flowable fill 345 bags, Rapid-set cement 246 bags | 30 min |
| C23 | 19.6 m | Not estimated (standard excavation depth) | Flowable fill + rapid-set cap | Compact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, Screed | Flowable fill 179 bags, Rapid-set cement 128 bags | 30 min |
| C24 | 17.6 m | Not estimated (standard excavation depth) | Flowable fill + rapid-set cap | Compact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, Screed | Flowable fill 145 bags, Rapid-set cement 103 bags | 30 min |
| F55 | 3.0 m | Not estimated (standard excavation depth) | Flowable fill + rapid-set cap | Compact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, Screed | Flowable fill 5 bags, Rapid-set cement 3 bags | 30 min |
| F196 | 3.0 m | Not estimated (standard excavation depth) | Flowable fill + rapid-set cap | Compact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, Screed | Flowable fill 5 bags, Rapid-set cement 3 bags | 30 min |
| F330 | 3.0 m | Not estimated (standard excavation depth) | Flowable fill + rapid-set cap | Compact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, Screed | Flowable fill 5 bags, Rapid-set cement 3 bags | 30 min |
| F338 | 3.0 m | Not estimated (standard excavation depth) | Flowable fill + rapid-set cap | Compact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, Screed | Flowable fill 5 bags, Rapid-set cement 3 bags | 30 min |
| F371 | 3.0 m | Not estimated (standard excavation depth) | Flowable fill + rapid-set cap | Compact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, Screed | Flowable fill 5 bags, Rapid-set cement 3 bags | 30 min |
| F391 | 3.0 m | Not estimated (standard excavation depth) | Flowable fill + rapid-set cap | Compact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, Screed | Flowable fill 5 bags, Rapid-set cement 3 bags | 30 min |
| F564 | 3.0 m | Not estimated (standard excavation depth) | Flowable fill + rapid-set cap | Compact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, Screed | Flowable fill 5 bags, Rapid-set cement 3 bags | 30 min |
| F640 | 3.0 m | Not estimated (standard excavation depth) | Flowable fill + rapid-set cap | Compact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, Screed | Flowable fill 5 bags, Rapid-set cement 3 bags | 30 min |
| F869 | 3.0 m | Not estimated (standard excavation depth) | Flowable fill + rapid-set cap | Compact track loader, Front-end loader, Line-of-sight rods, Wheel saw, Excavator, Telehandler, Water truck, Dump truck, Volumetric mixer, Screed | Flowable fill 5 bags, Rapid-set cement 3 bags | 30 min |
- Materials the plan orders
- Flowable fill 1052 bags, Rapid-set cement 752 bags, Fibreglass mat 0
- Materials the real damage needs
- Flowable fill 4036 bags, Rapid-set cement 322 bags, Fibreglass mat 0
Short: 0 bags of cement, 2984 bags of fill (another haul)
Methods, machines, material formulas and cure time come from the runway repair parameter table (version 2026.11-12); the solver decides which craters get the fibreglass mats.
What v2 changes, in plain words
- The detector is replaced by one learned from rendered runway damage; it looks at visible and thermal together and uses the thermal image at night.
- Each crater comes with a diameter and a depth, with an error range; material quantities use the estimated depth instead of always the standard excavation depth.
- It also tells spall, sub-munitions, debris and standing water apart; the current detector has no such classes.
- Everything else stays: a person still confirms each candidate, the strip and schedule use the same solver, methods and materials the same parameter table; v1's old runs replay unchanged.
Image-level measurement (576 test frames never used in training) · Seen in training
| Version | Found | Class also right | False alarms per 1,000 m² | Median relative diameter error |
|---|---|---|---|---|
| v1 current | 48.9% | 31.2% | 3.14 | 52.3% |
| v2 physical AI | 70.5% | 70% | 0.26 | 6.1% |
Comparison over 200 seeds (same damage) · Day · Seen in training
| Version | Craters found | UXO found | False alarms per run | Diameter error (mean / 90th pct) | Flyover to plan | Actual opening | Runs with damage missed in the strip (of which UXO) | Cement short (bags) |
|---|---|---|---|---|---|---|---|---|
| v1 current detector | 99.3% | 68.9% | 906.4 | 3.49 / 6.9 m | 275.1 min | 190 min | 43.5% (40.5%) | 0.0 |
| v2 physical AI (learned detection + size and depth) | 82.9% | 84.9% | 30.8 | 0.44 / 1.2 m | 7.5 min | 157 min | 74% (19%) | 48.2 |
Where v2 is worse or not yet to be trusted
- Day · Seen in training: Craters found v2 82.9%, v1 99.3%
- Day · Seen in training: Runs with damage missed in the strip (of which UXO) v2 74% (19%), v1 43.5% (40.5%)
- Day · Seen in training: Cement short (bags) v2 48.18, v1 0
- Day · Unseen (asphalt, rocket-type UXO, ball sub-munitions, round patches): Craters found v2 79.6%, v1 97.7%
- Day · Unseen (asphalt, rocket-type UXO, ball sub-munitions, round patches): Runs with damage missed in the strip (of which UXO) v2 84% (45%), v1 61% (55%)
- Day · Unseen (asphalt, rocket-type UXO, ball sub-munitions, round patches): Cement short (bags) v2 62.58, v1 0
- Night (thermal only) · Seen in training: Cement short (bags) v2 51.66, v1 31.85
- Night (thermal only) · Unseen (asphalt, rocket-type UXO, ball sub-munitions, round patches): Craters found v2 65.4%, v1 71.3%
- Night (thermal only) · Unseen (asphalt, rocket-type UXO, ball sub-munitions, round patches): Cement short (bags) v2 77.89, v1 39.74
- Image level · Seen in training · large craters (10 m and over): Found v2 65.7%, v1 94.0%
- Image level · Unseen (asphalt, rocket-type UXO, ball sub-munitions, round patches) · large craters (10 m and over): Found v2 57.7%, v1 84.6%
- Image level · Seen in training · craters: Found v2 82.7%, v1 92.7%
- Image level · Unseen (asphalt, rocket-type UXO, ball sub-munitions, round patches) · craters: Found v2 77.5%, v1 89.8%
- Unseen conditions: v2's find rate drops from 70.5% to 66.9% and false alarms rise from 0.26 to 0.32 per 1,000 m²; measure on real imagery of a new pavement or munition before relying on it.
- Every figure is measured on synthetic images; part of what the model learned may be features of this procedural geometry, and real-world performance is unknown.
Assumptions (not measured; other values may change the conclusion)
- A person spends 8 s per candidate
- A person wrongly accepts 10% of false alarms; each costs a crew 5 min
- True crater depth = diameter × 0.25
- Survey covers 75 m wide with 1.3× overlap; missed damage is found at the check before opening and then repaired