Runway readiness and budget

All aircraft off within

Recommended, NT$ 175.8 M: first aircraft off 1 h 5 min after the attack; all 12 off within 3 h in each of the 12 damage scenarios.

Budget and first aircraft off

50607080901000.00.51.01.52.02.53.0Package one-off purchase, without armoured EOD vehicles (NT$ 100 M)First aircraft (min)1234LRA
  • Other packages
  • Frontier
  • Levels 1–4 above
  • Lean / Recommended / Ample

Three packages: lean, recommended, ample

All three come from the same 648 packages, the cheapest that meets each rule below; armoured EOD vehicles and the waves of consumables kept are set per package (assumptions). Target as set at the top of the page: all aircraft off within 3 h.

The chart's x axis and the cards' "package one-off purchase" are one figure: repair sets, fibreglass mats, sweepers, drones and EOD team equipment, without armoured EOD vehicles; the vehicles are a separate line, then the total.

Lean

all aircraft off within 3 h on the twelve-scenario mean (the worst scenarios may exceed it)

1 repair set, 2 EOD teams, 1 sweeper, 3 drones, 0 mats

0 armoured EOD vehicles · consumables for 1 wave

Package one-off purchase (the chart's x axis)
NT$ 59.5 M
One-off purchase, total
NT$ 59.5 M
Annual upkeep
NT$ 2.4 M
Consumables stock
NT$ 10.1 M
First aircraft
1 h 14 min worst 2 h 17 min
All off
3 h 0 min worst 5 h 3 min
Within 1 h
1.4 aircraft
Within 2 h
8.3 aircraft

Against the smallest package: NT$ 6.8 M more one-off purchase; on the twelve-scenario mean, first aircraft 18 min earlier, 2 more within 2 h, all off 20 min earlier (the EOD vehicles' effect is under the submunition assumption).

Recommended

all aircraft off within 3 h in every one of the twelve scenarios

2 repair sets, 2 EOD teams, 1 sweeper, 3 drones, 0 mats

1 armoured EOD vehicle · consumables for 2 waves

Package one-off purchase (the chart's x axis)
NT$ 95.8 M
+ 1 armoured EOD vehicle (listed apart, not on the chart)
NT$ 80.0 M
One-off purchase, total
NT$ 175.8 M
Annual upkeep
NT$ 8.2 M
Consumables stock
NT$ 20.8 M
First aircraft
1 h 5 min worst 1 h 26 min
All off
2 h 18 min worst 2 h 59 min
Within 1 h
1.4 aircraft
Within 2 h
8.8 aircraft

Against Lean: NT$ 116.3 M more one-off purchase; on the twelve-scenario mean, first aircraft 10 min earlier, 0.5 more within 2 h, all off 41 min earlier (the EOD vehicles' effect is under the submunition assumption).

Ample

every scenario with 30 minutes to spare

4 repair sets, 1 EOD team, 2 sweepers, 2 drones, 1 mat

2 armoured EOD vehicles · consumables for 3 waves

Package one-off purchase (the chart's x axis)
NT$ 177.1 M
+ 2 armoured EOD vehicles (listed apart, not on the chart)
NT$ 160.0 M
One-off purchase, total
NT$ 337.1 M
Annual upkeep
NT$ 16.3 M
Consumables stock
NT$ 45.2 M
First aircraft
1 h 3 min worst 1 h 28 min
All off
1 h 52 min worst 2 h 25 min
Within 1 h
1.4 aircraft
Within 2 h
11.3 aircraft

Against Recommended: NT$ 161.3 M more one-off purchase; on the twelve-scenario mean, first aircraft 2 min earlier, 2.4 more within 2 h, all off 27 min earlier (the EOD vehicles' effect is under the submunition assumption).

Base package

Recommended: bill of materials

11 one-off items: 5 made in Taiwan, 3 imported, 3 not verified (country of origin on the award notice)

ItemSpecificationQtyUnit priceSubtotalCost typeMade inProcurementSource
ExcavatorTracked, 20 t class2NT$ 5,398,000NT$ 10,796,000One-off purchaseJapanDomestic (award on record)T1
Wheel loaderArticulated, 90 hp or more2NT$ 3,983,000NT$ 7,966,000One-off purchaseMade in TaiwanDomestic (award on record)T2
Dump truck17 t or more4NT$ 4,120,000NT$ 16,480,000One-off purchaseMade in TaiwanDomestic (award on record)T3
Vibratory rollerSingle drum, 10–12 t2NT$ 5,000,000NT$ 10,000,000One-off purchasenot verifiedDomestic (to be confirmed)assumed
Mobile mixerVolumetric concrete mixer2NT$ 9,500,000NT$ 19,000,000One-off purchasenot verifiedDomestic (to be confirmed)assumed
Crane truck15 t, carries and lays the mats2NT$ 4,228,560NT$ 8,457,120One-off purchaseMade in TaiwanDomestic (award on record)T6
Runway sweeperRunway / road sweeper1NT$ 9,970,000NT$ 9,970,000One-off purchaseMade in TaiwanDomestic (award on record)T4
Damage-assessment droneHigh-end survey drone (made in Taiwan)3NT$ 379,000NT$ 1,137,000One-off purchaseMade in TaiwanDomestic (award on record)T5
EOD team equipmentBomb suits, remote EOD robot, tools2NT$ 6,000,000NT$ 12,000,000One-off purchasenot verifiedDomestic (to be confirmed)assumed
Armoured UXO clearance vehicleThe type the US Air Force fields: mine-resistant chassis, 3 kW laser, stand-off neutralisation (model and specifications on the clearance-vehicle tab)1NT$ 80,000,000NT$ 80,000,000One-off purchaseUnited StatesUS channels only (FMS or DCS)R12derived from contract
Annual machine upkeep5 % of the machines' purchase price1NT$ 8,190,306NT$ 8,190,306Annual upkeep—Domestic (to be confirmed)assumed
Rapid-set concrete27.2 kg bags; 25.4 cm cap22,076NT$ 572NT$ 12,627,472Used per repairUnited StatesDomestic (to be confirmed)U2
Flowable fillAbout 0.76 m³ bulk bags; 35.6 cm fill502NT$ 15,000NT$ 7,530,000Used per repairnot verifiedDomestic (to be confirmed)assumed
Citric-acid retarder3 lb per rapid-set super sack (29.4 °C and above)1,073NT$ 60NT$ 64,380Used per repairnot verifiedDomestic (to be confirmed)assumed
White traffic paintMOS centre and end lines; 0.248 L per m908NT$ 150NT$ 136,200Used per repairnot verifiedDomestic (to be confirmed)assumed
Black obliteration paintCovers existing markings; 0.248 L per m908NT$ 150NT$ 136,200Used per repairnot verifiedDomestic (to be confirmed)assumed
Glass beadsOn the white lines; 0.298 kg per m1,090NT$ 60NT$ 65,400Used per repairnot verifiedDomestic (to be confirmed)assumed
AsphaltAsphalt cap (M2) reserve when rapid-set runs out, 10 cm (t)54NT$ 3,500NT$ 189,000Used per repairnot verifiedDomestic (to be confirmed)assumed
Spall repair materialSpall patch (M5), two spalls per bucket12NT$ 4,000NT$ 48,000Used per repairnot verifiedDomestic (to be confirmed)assumed
Package one-off purchase (the chart's x axis)NT$ 95,806,120
+ 1 armoured EOD vehicle (listed apart, not on the chart)NT$ 80,000,000
One-off purchase, totalNT$ 175,806,120
Annual upkeepNT$ 8,190,306
Consumables stockNT$ 20,796,652

Runway repair readiness: what it costs, how fast, how many aircraft

Computing: 0 / 48

Sensing runway: how much sooner the damage is found

The same twelve scenarios, with the drone survey of the whole runway replaced by fibre and impact sensing built into the runway, which places the impacts within minutes of the attack; the drones only fly to the flagged points to confirm crater size and tell a bomb from a mine. Machines and plans are unchanged. Sensing times are illustrative estimates.

Computing: 0 / 96

Repair resource calculators

Machines, material stock and UXO clearance for a typical attack. Every value can be changed; values marked “assumption” await the unit or public figures.

Computing… 0 / 12

Purchase and material prices

Equipment cost = number of each machine × unit price. EOD teams are personnel, not purchases. Materials per repair = rapid-set cement for each crater (its area × 30 cm) × unit price; craters under a mat take no cement, and mats are reused, so they are not counted per repair.

ItemUnit priceUnitMade inSource
Excavator (20 t class)NT$ 5,398,000eachJapanT1
Loader (skid-steer / wheel loader)NT$ 3,983,000eachMade in TaiwanT2
Dump truckNT$ 4,120,000eachMade in TaiwanT3
Vibratory rollerNT$ 5,000,000eachnot verifiedest.
Mobile concrete mixerNT$ 9,500,000eachnot verifiedest.
Crane truck (carries and lays the mats)NT$ 4,228,560eachMade in TaiwanT6
Repair mat (FRP / AM2, one crater)NT$ 5,006,784kitUnited StatesU1
Runway sweeperNT$ 9,970,000eachMade in TaiwanT4
Survey droneNT$ 379,000eachMade in TaiwanT5
High-strength rapid-set cement (27.2 kg bags, about 81 per m³)NT$ 46,226m³United StatesU2

Runway repair readiness: what it costs, how fast, how many aircraft

The same twelve runway damage scenarios, run once for each of four repair readiness levels. Each run uses the runway page's solvers: the plan that opens the whole strip soonest, and the plan that finishes a take-off segment soonest on any strip; the one with the smaller average aircraft wait counts. Cost has two parts: the equipment bought in peacetime (one-off) and the materials used by each repair.

  • Twelve damage scenarios
  • 12 aircraft waiting, 4 heavy, one off every 2 minutes
  • Rapid-set cap to aircraft traffic: system default 30 min (assumed, to be confirmed by the using unit) | published guidance 120 min at 4.5 °C and above
  • Prices from Taiwan procurement awards and US military price lists; those not found are marked estimates; US$1 = NT$32

A level meets the target only if it does so in every scenario.

  • Each scenario: the plan that opens the whole strip soonest (proven optimal), the plan that finishes a take-off segment soonest on any strip (proven optimal), and the take-off-first plan on the best strip; the one with the smallest average aircraft wait counts.
  • Equipment is a one-off peacetime purchase; upkeep, training and personnel are not counted. Materials are what each repair uses.
  • All figures are solver results for comparing readiness levels.
One scenario's aerial view, repair order and take-offs on the runway page →