- Read-out
- Washout: valley side of the road gone for about 17 m
- Machines
- Excavators × 1, Dump trucks × 2, Rollers × 1
- Order
- #2 · starts T+00:10, open T+04:23
- Footpath
- passable on foot T+02:20
- Cut off behind it
- 4,320 people, 36 patients · Jianshi, Meihua, Jinping, Naluo, Yulao, Tianpu, Yufeng, Xiuluan, Taigang, Xinguang, Cinsbu, Smangus
STRATA · Road repair ordering
Who gets reconnected first, worked out in the open.
After the typhoon, route 竹60 into Jianshi township and its branches are cut by landslides, rockfalls, washed-out roadbeds and damaged bridges. Excavators, loaders, dump trucks and the other repair machines leave the forward command post at Neiwan; each fleet is limited, a machine works one cut at a time, and none can pass a cut that is still closed. A drone maps every cut before work starts (orthophoto and 3D model, to estimate the volume); every branch road has lost mobile coverage, so a temporary comms node goes up first to give the crew voice and the command post live video. Where the machines cannot get through yet, a manual crew walks in ahead to prepare, or a helicopter lifts a small machine set in to work from the inner side. On the real road tree and settlement positions, this page works out the repair order and the moment each settlement gets its road back, and sets it beside the usual whiteboard rules.
- Damage is assumed; roads and settlements are real
- Population and medical figures are illustrative
- Work hours and the machines each kind of cut needs are illustrative
- Same seed, same result for anyone who reruns it
- Road data © OpenStreetMap contributors, ODbL
Everything below is computed live in your browser; any change recomputes it. seed 36
Recommended order
Weighted average time to reconnection
7 h 24 min
- Forward command post (Neiwan)
- Settlement
- Medical cases waiting
- Fork
- Cut (number = order)
The white lines on the imagery are the road tree from Neiwan into Jianshi (竹60, 竹61, 竹62, 竹60-1 and the Smangus road). Dots are settlements (orange ring = medical cases waiting); orange markers are cuts numbered in repair order, square markers are damaged bridges.
Source: assumed damage, seed 36 · 2 excavators, 1 breaker, 2 loaders, 4 trucks, 1 roller, 1 bridge crane · 2 drones · 25 km/h on mountain roads · computed live in the browser・2 comms teams・1 manual crew, 1 airlifted set · Roads and settlements: OpenStreetMap (data as of 2026-10-24) © OpenStreetMap contributors, ODbL · Imagery: Esri World Imagery (Esri, Vantor, Earthstar Geographics, and the GIS User Community)
| Order | Cut | Type | Where | Machines | Mapped | Start | Open | Reconnects |
|---|---|---|---|---|---|---|---|---|
| 1 | D8 | Landslide | 司馬庫斯產業道路 · 50.2 km from Neiwan | Airlifted small set 1 (helicopter-slung mini excavator and skid-steer, working from the inner side) | T+00:40 | T+02:00 | T+06:21 | Smangus |
| 2 | D1 | Washed-out roadbed | 120 中山街二段 · 1.3 km from Neiwan | Excavator 1, Truck 1+2, Roller 1 | T+00:10 | T+00:10 | T+04:23 | Jianshi, Naluo, Yulao, Tianpu, Xiuluan |
| 3 | D3 | Landslide | 竹62 梅花道路 · 8.5 km from Neiwan | Excavator 2, Loader 1, Truck 3+4 · manual crew 1 walks in first to prepare T+02:08–T+03:08 | T+00:26 | T+04:40 | T+07:26 | Meihua |
| 4 | D6 | Damaged bridge | 竹60 · 42.1 km from Neiwan | Excavator 1, Bridge crane 1 | T+01:05 | T+06:01 | T+13:52 | Taigang |
| 5 | D4 | Rockfall | 竹60-1 玉峰道路 · 25.6 km from Neiwan | Breaker 1, Loader 2 | T+01:10 | T+05:21 | T+06:25 | — |
| 6 | D5 | Landslide | 竹60-1 玉峰道路 · 29.0 km from Neiwan | Excavator 2, Loader 2, Truck 1+2 | T+01:37 | T+08:21 | T+12:14 | Yufeng |
| 7 | D2 | Landslide | 竹61 · 7.9 km from Neiwan | Excavator 2, Loader 1, Truck 3+4 · manual crew 1 walks in first to prepare T+03:32–T+04:32 | T+01:26 | T+13:07 | T+16:00 | Jinping |
| 8 | D7 | Landslide | 竹60 新光道路 · 46.1 km from Neiwan | Excavator 1, Loader 2, Truck 1+2 | T+02:06 | T+14:02 | T+17:37 | Xinguang, Cinsbu |
Dispatch from this table. A cut starts only when every machine it needs is on site; start times include hauling the machines from their previous cut (25 km/h on mountain roads), the wait for the cuts before it, and the wait for the drone survey.
Source: assumed damage, seed 36 · 2 excavators, 1 breaker, 2 loaders, 4 trucks, 1 roller, 1 bridge crane · 2 drones · 25 km/h on mountain roads · computed live in the browser・2 comms teams・1 manual crew, 1 airlifted set
Weight = population ÷ 100 + medical cases × 10. The weighted average above is these times averaged by weight.
One row per drone, comms team or machine. Drones map the damage and comms teams put a node on each road first; work starts when the whole set of machines is on site. Gaps are waits for the cut ahead, for the survey, or for the other machines the same cut needs. Manual crew rows show the walk in and the preparation; airlift rows show a small set working a cut from the inner side.
Source: assumed damage, seed 36 · 2 excavators, 1 breaker, 2 loaders, 4 trucks, 1 roller, 1 bridge crane · 2 drones · 25 km/h on mountain roads · computed live in the browser・2 comms teams・1 manual crew, 1 airlifted set
Computing…
Cuts the machines cannot reach yet: a manual crew (on foot at 4 km/h, able to pass cuts that are still closed) clears debris and fallen trees and sets up the work zone in one hour; if that is done before the machines arrive, their work there is 20% shorter. An airlifted small set (helicopter-slung mini excavator and skid-steer) goes only to a cut with another cut in front of it, never to a bridge, and works from the inner side without waiting for the road to open, half again slower than the full set; the first lift is ready after 2 hours (request, weather, rigging), the second 45 minutes later; lifted cuts head the plan, so the drones survey them and comms covers them first. All figures are illustrative.
Dispatch: who sends which machine, and when it gets there
The computer takes, from the dispatch registry, the machines that reach Neiwan first (the cheaper first when equally early), re-plans the repair order with their real arrival times, and writes a work order for every unit.
- Registry units, machine counts and mobilisation times are illustrative
- In use, the county's standing contracts and machine registry replace them
Machines are assumed to be at Neiwan from the start. Switch to the registry to see each unit's real arrival and its work order.
Survey imagery from the cuts is relayed hop by hop back to Neiwan. Each damaged road needs a tethered relay drone every 5 km from Neiwan, shared where roads share a stretch; each hop costs about 15 % of the throughput, and live video needs at least 4 Mbps, otherwise only photos get through.
All the roads need 17 relay drones; 12 available, 8 in place.
- 竹61: 2 hops, about 34 Mbps✓ live video
- 竹62: 2 hops, about 34 Mbps✓ live video
- 竹60-1: 6 hops, about 17.7 Mbps✓ live video
- 竹60: 10 hops, about 9.3 Mbps✕ not enough relay drones: no link (use a satellite terminal or mobile base station)
- 司馬庫斯產業道路: 11 hops, about 7.9 Mbps✕ not enough relay drones: no link (use a satellite terminal or mobile base station)
Evacuation: most people out soonest, patients to hospital before their deadlines
People can start coming out while the roads are still being repaired. Three channels run at once: helicopters carry only the patients the road cannot bring out in time; foot crews open paths across the cuts and residents who can walk go down to the first cut still closed to vehicles, where buses pick them up; once a road reopens, ambulances and buses bring out everyone else.
- Patient numbers and deadlines are illustrative
- Dialysis deadline: 72 h after the last session
- Vehicle and helicopter numbers and capacities are adjustable
Standing by
- Cut (impassable)
- Passable on foot
- Open to vehicles
- Helicopter
- Ambulance / bus
- Relay drone (blue: video, red: no link)
- Critical
- Dialysis
- Powered equipment
- Late
The number in each settlement is the people still there; the green ring is the share already out. Dots are patients (red cross: critical, blue drop: dialysis, yellow bolt: powered equipment), outlined by whether they make their deadline. Drag the time slider or press play to see helicopters, people on foot and vehicles.
The survey drones photograph every cut; the computer reads the kind and extent of the damage and decides the machines and the order. The photos are synthesised from the same damage data.
- Read-out
- Landslide: debris over about 26 m of road
- Machines
- Excavators × 1, Loaders × 1, Dump trucks × 2
- Order
- #7 · starts T+13:07, open T+16:00
- Footpath
- passable on foot T+05:28
- Cut off behind it
- 380 people, 3 patients · Jinping
- Read-out
- Landslide: debris over about 25 m of road
- Machines
- Excavators × 1, Loaders × 1, Dump trucks × 2
- Order
- #3 · starts T+04:40, open T+07:26
- Footpath
- passable on foot T+03:50
- Cut off behind it
- 650 people, 5 patients · Meihua
- Read-out
- Rockfall: 6 boulders, largest about 3.7 m
- Machines
- Hydraulic breakers × 1, Loaders × 1
- Order
- #5 · starts T+05:21, open T+06:25
- Footpath
- no footpath (waits for the road)
- Cut off behind it
- 260 people, 2 patients · Yufeng
- Read-out
- Landslide: debris over about 28 m of road
- Machines
- Excavators × 1, Loaders × 1, Dump trucks × 2
- Order
- #6 · starts T+08:21, open T+12:14
- Footpath
- no footpath (waits for the road)
- Cut off behind it
- 260 people, 2 patients · Yufeng
- Read-out
- Bridge: one span down, about 6 m
- Machines
- Cranes + steel bridge × 1, Excavators × 1
- Order
- #4 · starts T+06:01, open T+13:52
- Footpath
- no footpath (waits for the road)
- Cut off behind it
- 440 people, 5 patients · Taigang, Xinguang, Cinsbu
- Read-out
- Landslide: debris over about 26 m of road
- Machines
- Excavators × 1, Loaders × 1, Dump trucks × 2
- Order
- #8 · starts T+14:02, open T+17:37
- Footpath
- passable on foot T+15:22
- Cut off behind it
- 290 people, 3 patients · Xinguang, Cinsbu
- Read-out
- Landslide: debris over about 21 m of road
- Machines
- Excavators × 1, Loaders × 1, Dump trucks × 2
- Order
- #1 · starts T+02:00, open T+06:21
- Footpath
- no footpath (waits for the road)
- Cut off behind it
- 180 people, 2 patients · Smangus
- Road only · T+59:38 · 31 / 36
- Road + on foot · T+54:46 · 31 / 36
- Road + helicopter · T+59:38 · 36 / 36
- All three · T+54:46 · 36 / 36
The same road-repair schedule, different evacuation channels. The earlier a curve rises, the better.
- +1 helicopterNo change
- +1 foot creweveryone out 28 min sooner
- +1 ambulanceNo change
- +1 buseveryone out 10 h 16 min sooner
One row per patient, by deadline. The tick is the deadline, the bar the arrival at hospital, coloured by channel; late arrivals are marked red.
Evacuation: most people out soonest, patients to hospital before their deadlines
- Helicopters: one landing zone per sortie, up to 4 people, 200 km/h, 15 min to load, available from 90 min; first the patients the road would bring out after their deadline (earliest deadline first), then those the road would bring out latest.
- On foot: foot crews walk in from Neiwan (4 km/h) and make each cut passable (rockfall 45 min, landslide 90, washed-out roadbed 120, ropes over a broken bridge 240), cuts with the most people behind first. Once a whole road is passable, residents who can walk (3 km/h, up to 8 km) go down to the nearest cut still closed to vehicles and a bus takes them on.
- By road: once a settlement is reconnected, ambulances (2 patients) and buses (40 people) shuttle from Neiwan, 15 min to load; patients go on 30 min to Zhudong hospital.
- The road-repair schedule is the proven-best one above; the evacuation is arranged by these rules and is not proven optimal.
What this response costs
Item by item from the repair and evacuation plan actually run: machines, materials, labour, helicopters and vehicles, survey and relay communications. Every unit price carries its source.
- Unit prices from public emergency contracts, the Public Construction Commission and published fee scales
- The ×1.3 mountain factor is an estimate
- Army support is shown as an equivalent cost, outside the county's spending
- Machines NT$ 876,285(14%)
- Materials NT$ 3.8 M(62%)
- Labour NT$ 62,520(1%)
- Evacuation NT$ 1.0 M(17%)
- Survey and comms NT$ 350,000(6%)
Blue is machine time on the cut, yellow its materials (including a steel bridge). Driving, standby and mobilisation are in the totals.
Line items and sources
| Category | Item | Quantity | Unit price | Amount | Source |
|---|---|---|---|---|---|
| Machines | Excavator (with operator) | 5 8-h units | NT$ 12,457 | NT$ 62,283 | S1 |
| Machines | Machine transport (per machine) | 11 each | NT$ 3,628 | NT$ 39,908 | S1 |
| Machines | Breaker | 1 8-h units | NT$ 20,560 | NT$ 20,560 | S1 |
| Machines | Loader | 5 8-h units | NT$ 14,513 | NT$ 72,566 | S1 |
| Machines | Dump truck | 10 8-h units | NT$ 12,457 | NT$ 124,566 | S1 |
| Machines | Vibratory roller | 1 8-h units | NT$ 21,320 | NT$ 21,320 | S2 |
| Machines | Crane (bridge) | 2 8-h units | NT$ 12,541 | NT$ 25,082 | S1 |
| Machines | Helicopter flight hours | 1.5 h | NT$ 340,000 | NT$ 510,000 | S15 |
| Materials | Aggregate fill | 170 m³ | NT$ 1,889 | NT$ 321,130 | S1 |
| Materials | Road surface patch | 79.5 m² | NT$ 1,209 | NT$ 96,116 | S1 |
| Materials | Bulk bags | 126 each | NT$ 1,000 | NT$ 126,000 | est. |
| Materials | Sandbags | 500 each | NT$ 140 | NT$ 70,000 | S1 |
| Materials | Temporary steel bridge | 12 m | NT$ 267,000 | NT$ 3,204,000 | S4 |
| Labour | Skilled workers (manual and foot crews) | 24 8-h units | NT$ 2,605 | NT$ 62,520 | S1 |
| Evacuation | Helicopter flight hours | 2.1 h | NT$ 340,000 | NT$ 704,875 | S15 |
| Evacuation | Coaches | 22 days | NT$ 14,000 | NT$ 308,000 | S12 |
| Evacuation | Ambulance (per trip) | 7 trips | NT$ 800 | NT$ 5,600 | S14 |
| Evacuation | Ambulance distance | 314.3 km | NT$ 25 | NT$ 7,856 | S14 |
| Survey and comms | Survey drones | 2 days | NT$ 35,000 | NT$ 70,000 | S16 |
| Survey and comms | Relay drones | 8 days | NT$ 35,000 | NT$ 280,000 | est. |
- S1 臺中市東區公所 115 年度天然災害搶修開口契約 標價清單(2026)
- S2 臺北市政府 112 年度工程預算參考單價分析表(2023)
- S15 中央社:空勤總隊黑鷹直升機每飛行小時約 34 萬(2025)
- S4 南投梅村部落聯外鋼便橋(30 m,800 萬,2024)
- S12 43 人座遊覽車包車報價(2026)
- S14 臺北市救護車收費基準
- S16 國土管理署 無人機空拍委外(每次約 3.5 萬)
- S3 監察院 五峰鄉災害搶修案(山地鄉機具二次轉運) · machines often have to be trans-shipped into mountain townships, so prices run higher; ×1.3 here (estimate)
- S21 災害防救法 第 30–34 條(徵調、徵用與補償) · basis for compensating requisitioned private machines, at government rates first
STRATA on top, the tools it calls underneath
In a disaster operations room STRATA does not “think up” an order. It hands the question to tools that can compute it and lays out three courses of action with their numbers and sources for a person to approve. This page is the real screen of one of those tools: road repair ordering.
Same damage map, same people, three orderings. STRATA does not choose for the commander; it makes the difference plain.
Intelligence → cut list
Simulated input on this pageDrone imagery, reports from village heads and residents, highway bureau reports: de-duplicated, with sources and uncertainty marked.
Road network and settlements
Computed on this pageOpenStreetMap road tree, settlement positions and distances; population and medical figures are illustrative here and come from household and clinic records in production.
Drone survey scheduling
Computed on this pageEvery cut is looked at before work starts; flight time from straight-line distance, assigned to the first free drone.
Repair ordering engine
Computed on this pageThe weighted-fastest order among all dispatch orders that respect the road, with its proof and comparisons.
Three courses of action → approval
Computed on this pageFastest, medical cases first, near to far, each with numbers; dispatched only after the commander approves.
Field reports → recompute
Being integratedTeams report progress and new cuts, the whole table recomputes; the commander sees the difference, not a fresh start.
Three courses of action (for approval)
| Course of action | Weighted average | Medical settlements all reconnected | Last reconnected |
|---|---|---|---|
| COA 1: weighted fastest (recommended) | 7 h 24 min | T+17:37 | T+17:37 |
| COA 2: medical cases first | 9 h 23 min · 1 h 59 min slower (+27%) | T+21:03 | T+21:36 |
| COA 3: near to far | 8 h 43 min · 1 h 19 min slower (+18%) | T+20:04 | T+20:04 |
This page produces courses of action only; dispatch needs the commander's approval.
Against the whiteboard rules
Same damage map, same crews, ordered the way a staff would on a whiteboard. Then 2,000 random orders that respect the road: the best order should sit at the far left with nothing beating it.
Weighted average time of 2,000 random orders
Computing…
Source: assumed damage, seed 36 · 2 excavators, 1 breaker, 2 loaders, 4 trucks, 1 roller, 1 bridge crane · 2 drones · 25 km/h on mountain roads · computed live in the browser・2 comms teams・1 manual crew, 1 airlifted set · Comparison: four whiteboard rules and 2,000 random orders, same simulation
Where adding an excavator stops paying
Same damage map and the other fleets unchanged, one to five excavators, each point solved to the best. A spare machine can stand down, so the time never rises when machines are added.
Computing…
Does the recommendation survive a change of assumptions?
Work hours, fleet sizes and drone count are assumptions, so each is changed on its own to see whether the order changes and how the original order fares.
Computing…
Method and limits
- The road tree comes from OpenStreetMap (extracted 2026-10-24): shortest paths from Neiwan to each settlement, split at settlements and forks, simplified to 8 m. Imagery is Esri World Imagery.
- Cuts, work hours, fleet sizes, population and medical figures are assumed; a rerun changes only those, never the roads or the settlements.
- Rules: a cut is mapped by a drone before work starts (orthophoto and 3D, to estimate the volume); beyond the command post's own road there is no mobile coverage, so each road (竹60, 竹61, 竹62, 竹60-1, the Smangus road) needs a temporary node — tethered relay drone, portable base station or satellite terminal — set up by a comms team before its cuts are worked, with live video back to the command post; each cut needs a set of machines on site together (landslide: excavator + loader + 2 dump trucks; rockfall: hydraulic breaker + loader; washed-out roadbed: excavator + 2 dump trucks + roller; damaged bridge: crane with a steel bridge set + excavator for the abutments), and a machine works one cut at a time; machines cannot pass a closed cut, so cuts nearer Neiwan open first.
- Objective: the weighted sum of reconnection times (weight = population ÷ 100 + medical cases × 10), ties broken by the last reconnection.
- Solver: branch and bound over every dispatch order that respects the road, with a fixed dispatch rule (each kind of machine sent from the unit that can be on site earliest). “Proven” means no better order under that rule; another rule means another run.
- The whiteboard rules, 2,000 random orders, the excavator sweep and the sensitivity cases all run through the same simulation.
- Cuts the machines cannot reach yet: a manual crew (on foot at 4 km/h, able to pass cuts that are still closed) clears debris and fallen trees and sets up the work zone in one hour; if that is done before the machines arrive, their work there is 20% shorter. An airlifted small set (helicopter-slung mini excavator and skid-steer) goes only to a cut with another cut in front of it, never to a bridge, and works from the inner side without waiting for the road to open, half again slower than the full set; the first lift is ready after 2 hours (request, weather, rigging), the second 45 minutes later; lifted cuts head the plan, so the drones survey them and comms covers them first. All figures are illustrative.