all aircraft off within 3 h on the twelve-scenario mean (the worst scenarios may exceed it) · Data version runway-budget/v1
Keep runway repair machines, EOD equipment and consumables in peacetime so that, after an attack on the runway, all 12 waiting aircraft are off within 3 h of the start of the damage assessment, with the first aircraft off as early as possible.
Against the smallest package: NT$ 6.8 M more one-off purchase; on the twelve-scenario mean, first aircraft 18 min earlier, 2 more within 2 h, all off 20 min earlier (the EOD vehicles' effect is under the submunition assumption).
| Item | Specification | Qty | Unit price | Subtotal | Cost type | Made in | Procurement | Need | Effect | Source |
|---|---|---|---|---|---|---|---|---|---|---|
| Excavator | Tracked, 20 t class | 1 | 5,398,000 | 5,398,000 | One-off purchase | Japan | Domestic (award on record) | 1 repair sets × 1 each; the number of sets is the number of craters worked at once | Already the minimum | T1 |
| Wheel loader | Articulated, 90 hp or more | 1 | 3,983,000 | 3,983,000 | One-off purchase | Made in Taiwan | Domestic (award on record) | 1 repair sets × 1 each; the number of sets is the number of craters worked at once | Already the minimum | T2 |
| Dump truck | 17 t or more | 2 | 4,120,000 | 8,240,000 | One-off purchase | Made in Taiwan | Domestic (award on record) | 1 repair sets × 2 each; the number of sets is the number of craters worked at once | Already the minimum | T3 |
| Vibratory roller | Single drum, 10–12 t | 1 | 5,000,000 | 5,000,000 | One-off purchase | not verified | Domestic (to be confirmed) | 1 repair sets × 1 each; the number of sets is the number of craters worked at once | Already the minimum | assumed |
| Mobile mixer | Volumetric concrete mixer | 1 | 9,500,000 | 9,500,000 | One-off purchase | not verified | Domestic (to be confirmed) | 1 repair sets × 1 each; the number of sets is the number of craters worked at once | Already the minimum | assumed |
| Crane truck | 15 t, carries and lays the mats | 1 | 4,228,560 | 4,228,560 | One-off purchase | Made in Taiwan | Domestic (award on record) | 1 repair sets × 1 each; the number of sets is the number of craters worked at once | Already the minimum | T6 |
| Runway sweeper | Runway / road sweeper | 1 | 9,970,000 | 9,970,000 | One-off purchase | Made in Taiwan | Domestic (award on record) | Debris swept before the strip opens; 1 sweeping in sections | Already the minimum | T4 |
| Damage-assessment drone | High-end survey drone (made in Taiwan) | 3 | 379,000 | 1,137,000 | One-off purchase | Made in Taiwan | Domestic (award on record) | Damage assessment after the attack; 3 flying sections, about 8 min | One unit less: first aircraft 4 min later, 0.2 fewer within 2 h, all off 4 min later | T5 |
| EOD team equipment | Bomb suits, remote EOD robot, tools | 2 | 6,000,000 | 12,000,000 | One-off purchase | not verified | Domestic (to be confirmed) | 2 EOD teams clearing UXO at the same time | One unit less: first aircraft 2 min later, 0.1 fewer within 2 h, all off 4 min later | assumed |
| Annual machine upkeep | 5 % of the machines' purchase price | 1 | 2,372,828 | 2,372,828 | Annual upkeep | — | Domestic (to be confirmed) | Keeps the machines serviceable | — | assumed |
| Rapid-set concrete | 27.2 kg bags; 25.4 cm cap | 10,708 | 572 | 6,124,976 | Used per repair | United States | Domestic (to be confirmed) | Worst wave × 1 waves × 120% | Lasts 1 worst-case waves | U2 |
| Flowable fill | About 0.76 m³ bulk bags; 35.6 cm fill | 244 | 15,000 | 3,660,000 | Used per repair | not verified | Domestic (to be confirmed) | Worst wave × 1 waves × 120% | Lasts 1 worst-case waves | assumed |
| Citric-acid retarder | 3 lb per rapid-set super sack (29.4 °C and above) | 522 | 60 | 31,320 | Used per repair | not verified | Domestic (to be confirmed) | 3 lb per rapid-set super sack; 1 waves × 120% | Lasts 1 worst-case waves | assumed |
| White traffic paint | MOS centre and end lines; 0.248 L per m | 454 | 150 | 68,100 | Used per repair | not verified | Domestic (to be confirmed) | 1,524 m of strip marked per wave; 1 waves × 120% | Lasts 1 worst-case waves | assumed |
| Black obliteration paint | Covers existing markings; 0.248 L per m | 454 | 150 | 68,100 | Used per repair | not verified | Domestic (to be confirmed) | 1,524 m of strip marked per wave; 1 waves × 120% | Lasts 1 worst-case waves | assumed |
| Glass beads | On the white lines; 0.298 kg per m | 545 | 60 | 32,700 | Used per repair | not verified | Domestic (to be confirmed) | 1,524 m of strip marked per wave; 1 waves × 120% | Lasts 1 worst-case waves | assumed |
| Asphalt | Asphalt cap (M2) reserve when rapid-set runs out, 10 cm (t) | 27 | 3,500 | 94,500 | Used per repair | not verified | Domestic (to be confirmed) | Asphalt cap (M2) reserve for 20% of the capped craters; 1 waves × 120% | Lasts 1 worst-case waves | assumed |
| Spall repair material | Spall patch (M5), two spalls per bucket | 6 | 4,000 | 24,000 | Used per repair | not verified | Domestic (to be confirmed) | 10 spalls per wave (M5); 1 waves × 120% | Lasts 1 worst-case waves | assumed |
| Cut | Saves | First aircraft | Off within 2 h | All off |
|---|---|---|---|---|
| One EOD team less (2 → 1) | NT$ 6,000,000 | +2 min | −0.1 | +4 min |
| One drone less (3 → 2) | NT$ 379,000 | +4 min | −0.2 | +4 min |
Prepared from public sources and solver results; it holds no data of any unit or base.