← Readiness and budget

Runway repair readiness: budget request (Lean)

all aircraft off within 3 h on the twelve-scenario mean (the worst scenarios may exceed it) · Data version runway-budget/v1

1. Requirement

Keep runway repair machines, EOD equipment and consumables in peacetime so that, after an attack on the runway, all 12 waiting aircraft are off within 3 h of the start of the damage assessment, with the first aircraft off as early as possible.

2. Expected effect

Base package
1 repair set, 2 EOD teams, 1 sweeper, 3 drones, 0 mats · 0 armoured EOD vehicles · consumables for 1 wave
First aircraft
1 h 14 min (worst 2 h 17 min)
All off
3 h 0 min (worst 5 h 3 min)
Within 1 h
1.4 aircraft
Within 2 h
8.3 aircraft

Against the smallest package: NT$ 6.8 M more one-off purchase; on the twelve-scenario mean, first aircraft 18 min earlier, 2 more within 2 h, all off 20 min earlier (the EOD vehicles' effect is under the submunition assumption).

3. Funds required

Package one-off purchase (the chart's x axis)
NT$ 59,456,560
One-off purchase, total
NT$ 59,456,560
Annual upkeep
NT$ 2,372,828
Consumables stock
NT$ 10,103,696

4. Items

ItemSpecificationQtyUnit priceSubtotalCost typeMade inProcurementNeedEffectSource
ExcavatorTracked, 20 t class15,398,0005,398,000One-off purchaseJapanDomestic (award on record)1 repair sets × 1 each; the number of sets is the number of craters worked at onceAlready the minimumT1
Wheel loaderArticulated, 90 hp or more13,983,0003,983,000One-off purchaseMade in TaiwanDomestic (award on record)1 repair sets × 1 each; the number of sets is the number of craters worked at onceAlready the minimumT2
Dump truck17 t or more24,120,0008,240,000One-off purchaseMade in TaiwanDomestic (award on record)1 repair sets × 2 each; the number of sets is the number of craters worked at onceAlready the minimumT3
Vibratory rollerSingle drum, 10–12 t15,000,0005,000,000One-off purchasenot verifiedDomestic (to be confirmed)1 repair sets × 1 each; the number of sets is the number of craters worked at onceAlready the minimumassumed
Mobile mixerVolumetric concrete mixer19,500,0009,500,000One-off purchasenot verifiedDomestic (to be confirmed)1 repair sets × 1 each; the number of sets is the number of craters worked at onceAlready the minimumassumed
Crane truck15 t, carries and lays the mats14,228,5604,228,560One-off purchaseMade in TaiwanDomestic (award on record)1 repair sets × 1 each; the number of sets is the number of craters worked at onceAlready the minimumT6
Runway sweeperRunway / road sweeper19,970,0009,970,000One-off purchaseMade in TaiwanDomestic (award on record)Debris swept before the strip opens; 1 sweeping in sectionsAlready the minimumT4
Damage-assessment droneHigh-end survey drone (made in Taiwan)3379,0001,137,000One-off purchaseMade in TaiwanDomestic (award on record)Damage assessment after the attack; 3 flying sections, about 8 minOne unit less: first aircraft 4 min later, 0.2 fewer within 2 h, all off 4 min laterT5
EOD team equipmentBomb suits, remote EOD robot, tools26,000,00012,000,000One-off purchasenot verifiedDomestic (to be confirmed)2 EOD teams clearing UXO at the same timeOne unit less: first aircraft 2 min later, 0.1 fewer within 2 h, all off 4 min laterassumed
Annual machine upkeep5 % of the machines' purchase price12,372,8282,372,828Annual upkeep—Domestic (to be confirmed)Keeps the machines serviceable—assumed
Rapid-set concrete27.2 kg bags; 25.4 cm cap10,7085726,124,976Used per repairUnited StatesDomestic (to be confirmed)Worst wave × 1 waves × 120%Lasts 1 worst-case wavesU2
Flowable fillAbout 0.76 m³ bulk bags; 35.6 cm fill24415,0003,660,000Used per repairnot verifiedDomestic (to be confirmed)Worst wave × 1 waves × 120%Lasts 1 worst-case wavesassumed
Citric-acid retarder3 lb per rapid-set super sack (29.4 °C and above)5226031,320Used per repairnot verifiedDomestic (to be confirmed)3 lb per rapid-set super sack; 1 waves × 120%Lasts 1 worst-case wavesassumed
White traffic paintMOS centre and end lines; 0.248 L per m45415068,100Used per repairnot verifiedDomestic (to be confirmed)1,524 m of strip marked per wave; 1 waves × 120%Lasts 1 worst-case wavesassumed
Black obliteration paintCovers existing markings; 0.248 L per m45415068,100Used per repairnot verifiedDomestic (to be confirmed)1,524 m of strip marked per wave; 1 waves × 120%Lasts 1 worst-case wavesassumed
Glass beadsOn the white lines; 0.298 kg per m5456032,700Used per repairnot verifiedDomestic (to be confirmed)1,524 m of strip marked per wave; 1 waves × 120%Lasts 1 worst-case wavesassumed
AsphaltAsphalt cap (M2) reserve when rapid-set runs out, 10 cm (t)273,50094,500Used per repairnot verifiedDomestic (to be confirmed)Asphalt cap (M2) reserve for 20% of the capped craters; 1 waves × 120%Lasts 1 worst-case wavesassumed
Spall repair materialSpall patch (M5), two spalls per bucket64,00024,000Used per repairnot verifiedDomestic (to be confirmed)10 spalls per wave (M5); 1 waves × 120%Lasts 1 worst-case wavesassumed

Cuts: one unit less

CutSavesFirst aircraftOff within 2 hAll off
One EOD team less (2 → 1)NT$ 6,000,000+2 min−0.1+4 min
One drone less (3 → 2)NT$ 379,000+4 min−0.2+4 min

5. Basis of calculation

6. Assumptions

7. Sources

Prepared from public sources and solver results; it holds no data of any unit or base.