every scenario with 30 minutes to spare · Data version runway-budget/v1
Keep runway repair machines, EOD equipment and consumables in peacetime so that, after an attack on the runway, all 12 waiting aircraft are off within 3 h of the start of the damage assessment, with the first aircraft off as early as possible.
Against Recommended: NT$ 161.3 M more one-off purchase; on the twelve-scenario mean, first aircraft 2 min earlier, 2.4 more within 2 h, all off 27 min earlier (the EOD vehicles' effect is under the submunition assumption).
| Item | Specification | Qty | Unit price | Subtotal | Cost type | Made in | Procurement | Need | Effect | Source |
|---|---|---|---|---|---|---|---|---|---|---|
| Excavator | Tracked, 20 t class | 4 | 5,398,000 | 21,592,000 | One-off purchase | Japan | Domestic (award on record) | 4 repair sets × 1 each; the number of sets is the number of craters worked at once | One set less: first aircraft 0 min later, 0.8 fewer within 2 h, all off 11 min later | T1 |
| Wheel loader | Articulated, 90 hp or more | 4 | 3,983,000 | 15,932,000 | One-off purchase | Made in Taiwan | Domestic (award on record) | 4 repair sets × 1 each; the number of sets is the number of craters worked at once | One set less: first aircraft 0 min later, 0.8 fewer within 2 h, all off 11 min later | T2 |
| Dump truck | 17 t or more | 8 | 4,120,000 | 32,960,000 | One-off purchase | Made in Taiwan | Domestic (award on record) | 4 repair sets × 2 each; the number of sets is the number of craters worked at once | One set less: first aircraft 0 min later, 0.8 fewer within 2 h, all off 11 min later | T3 |
| Vibratory roller | Single drum, 10–12 t | 4 | 5,000,000 | 20,000,000 | One-off purchase | not verified | Domestic (to be confirmed) | 4 repair sets × 1 each; the number of sets is the number of craters worked at once | One set less: first aircraft 0 min later, 0.8 fewer within 2 h, all off 11 min later | assumed |
| Mobile mixer | Volumetric concrete mixer | 4 | 9,500,000 | 38,000,000 | One-off purchase | not verified | Domestic (to be confirmed) | 4 repair sets × 1 each; the number of sets is the number of craters worked at once | One set less: first aircraft 0 min later, 0.8 fewer within 2 h, all off 11 min later | assumed |
| Crane truck | 15 t, carries and lays the mats | 4 | 4,228,560 | 16,914,240 | One-off purchase | Made in Taiwan | Domestic (award on record) | 4 repair sets × 1 each; the number of sets is the number of craters worked at once | One set less: first aircraft 0 min later, 0.8 fewer within 2 h, all off 11 min later | T6 |
| Crater repair mat | FRP composite, one per crater (first wave) | 1 | 5,006,784 | 5,006,784 | One-off purchase | United States | Domestic to be confirmed; US reference price | The last craters of the first wave opened under a mat without curing; 1 craters | One unit less: first aircraft 0 min later, 0.5 fewer within 2 h, all off 8 min later | U1 |
| Runway sweeper | Runway / road sweeper | 2 | 9,970,000 | 19,940,000 | One-off purchase | Made in Taiwan | Domestic (award on record) | Debris swept before the strip opens; 2 sweeping in sections | One unit less: first aircraft 5 min later, 1.3 fewer within 2 h, all off 11 min later | T4 |
| Damage-assessment drone | High-end survey drone (made in Taiwan) | 2 | 379,000 | 758,000 | One-off purchase | Made in Taiwan | Domestic (award on record) | Damage assessment after the attack; 2 flying sections, about 12 min | One unit less: first aircraft 12 min later, 1.3 fewer within 2 h, all off 12 min later | T5 |
| EOD team equipment | Bomb suits, remote EOD robot, tools | 1 | 6,000,000 | 6,000,000 | One-off purchase | not verified | Domestic (to be confirmed) | 1 EOD teams clearing UXO at the same time | Already the minimum | assumed |
| Armoured UXO clearance vehicle | The type the US Air Force fields: mine-resistant chassis, 3 kW laser, stand-off neutralisation (model and specifications on the clearance-vehicle tab) | 2 | 80,000,000 | 160,000,000 | One-off purchase | United States | US channels only (FMS or DCS) | Clears scattered submunitions from the take-off segment with no one on foot | With the submunition assumption, first aircraft 7 h 50 min earlier (0 → this number, assumed blade) | R12(derived from contract) |
| Annual machine upkeep | 5 % of the machines' purchase price | 1 | 16,304,812 | 16,304,812 | Annual upkeep | — | Domestic (to be confirmed) | Keeps the machines serviceable | — | assumed |
| Rapid-set concrete | 27.2 kg bags; 25.4 cm cap | 30,672 | 572 | 17,544,384 | Used per repair | United States | Domestic (to be confirmed) | Worst wave × 3 waves × 120% | Lasts 3 worst-case waves | U2 |
| Flowable fill | About 0.76 m³ bulk bags; 35.6 cm fill | 753 | 15,000 | 11,295,000 | Used per repair | not verified | Domestic (to be confirmed) | Worst wave × 3 waves × 120% | Lasts 3 worst-case waves | assumed |
| Mats for further waves | FRP composite, one per crater (from the second wave) | 3 | 5,006,784 | 15,020,352 | Used per repair | United States | Domestic to be confirmed; US reference price | Mats stay until the permanent repair; kept for waves 2 onward (3 waves) | Lasts 3 worst-case waves | U1 |
| Mat anchoring kit | Per mat: 54 anchors, 54 anchor and 108 joining bushings, about 7 rock bits | 4 | 50,000 | 200,000 | Used per repair | not verified | Domestic (to be confirmed) | One per mat laid, the first wave included; 3 waves × 120% | Lasts 3 worst-case waves | assumed |
| Citric-acid retarder | 3 lb per rapid-set super sack (29.4 °C and above) | 1,491 | 60 | 89,460 | Used per repair | not verified | Domestic (to be confirmed) | 3 lb per rapid-set super sack; 3 waves × 120% | Lasts 3 worst-case waves | assumed |
| White traffic paint | MOS centre and end lines; 0.248 L per m | 1,361 | 150 | 204,150 | Used per repair | not verified | Domestic (to be confirmed) | 1,524 m of strip marked per wave; 3 waves × 120% | Lasts 3 worst-case waves | assumed |
| Black obliteration paint | Covers existing markings; 0.248 L per m | 1,361 | 150 | 204,150 | Used per repair | not verified | Domestic (to be confirmed) | 1,524 m of strip marked per wave; 3 waves × 120% | Lasts 3 worst-case waves | assumed |
| Glass beads | On the white lines; 0.298 kg per m | 1,635 | 60 | 98,100 | Used per repair | not verified | Domestic (to be confirmed) | 1,524 m of strip marked per wave; 3 waves × 120% | Lasts 3 worst-case waves | assumed |
| Crushed stone | Compacted under the fibreglass mats (M3), three 18 cm lifts (m³) | 200 | 1,200 | 240,000 | Used per repair | not verified | Domestic (to be confirmed) | Crushed stone under every mat (M3); 3 waves × 120% | Lasts 3 worst-case waves | assumed |
| Asphalt | Asphalt cap (M2) reserve when rapid-set runs out, 10 cm (t) | 75 | 3,500 | 262,500 | Used per repair | not verified | Domestic (to be confirmed) | Asphalt cap (M2) reserve for 20% of the capped craters; 3 waves × 120% | Lasts 3 worst-case waves | assumed |
| Spall repair material | Spall patch (M5), two spalls per bucket | 18 | 4,000 | 72,000 | Used per repair | not verified | Domestic (to be confirmed) | 10 spalls per wave (M5); 3 waves × 120% | Lasts 3 worst-case waves | assumed |
| Cut | Saves | First aircraft | Off within 2 h | All off |
|---|---|---|---|---|
| One mat less (1 → 0) | NT$ 5,006,784 | +0 min | −0.5 | +8 min |
| One repair set less (4 → 3) | NT$ 36,349,560 | +0 min | −0.7 | +11 min |
| One sweeper less (2 → 1) | NT$ 9,970,000 | +5 min | −1.3 | +11 min |
| One drone less (2 → 1) | NT$ 379,000 | +12 min | −1.3 | +12 min |
Prepared from public sources and solver results; it holds no data of any unit or base.